(TLCF) Hope College Visual Progress Report |
|
Organisation Name: |
Hope Of The Gold Coast Ltd. |
|
||||
Project Name: |
Hope College Renovations |
|
||||
Project Address: |
B4/ 175 Varsity Parade Varsity Lakes Queensland 4227 |
|
||||
|
|
|
||||
Milestone Details |
Proposed |
Proposed |
||||
Commencement of the project |
30/08/2009 |
n/a |
||||
Acquire plan for Auditorium refurbishment |
30/08/2009 |
25/09/2009 |
||||
Receipt of quotes for auditorium refurbishment |
1/10/2009 |
19/10/2009 |
||||
Patio - Acquire Engineering plans |
25/10/2009 |
30/10/2009 |
||||
Patio - Seek Council Approval |
25/10/2009 |
15/12/2009 |
||||
Mezzanine - Order Steal |
11/11/2009 |
11/12/2009 |
||||
Mezzanine - Builder to order other matereals such as wood, carpet |
20/11/2009 |
12/12/2009 |
||||
Mezzanine - Order of seats and tablets |
22/11/2009 |
12/12/2009 |
||||
Computer Fit Out Pt 1 - buying server, Hard drives, and labour |
1/12/2009 |
15/01/2010 |
||||
Patio - Order materials such as Concrete, tiles and soft fall |
15/12/2009 |
15/01/2010 |
||||
Mezzanine - Builder to Commence |
15/12/2009 |
15/02/2009 |
||||
Computer Fit Out Pt 2 - buying wireless equipment, computer terminal, software and labour |
16/01/2010 |
15/03/2010 |
||||
Patio - Poring of concrete |
18/01/2010 |
22/01/2009 |
||||
Patio - Erecting steel framing and roofing |
25/01/2010 |
3/02/2010 |
||||
Patio - Tiling |
|
10/02/2010 |
25/02/2010 |
|||
Mezzanine - Seats to be fitted |
20/02/2009 |
28/02/2009 |
||||
Patio - Poring of Soft fall |
28/02/2010 |
15/03/2010 |
||||
|
|
|
||||
Completion of the project |
n/a |
15/03/2009 |
||||
Totals |
|
|
||||
Mezzanine Plans designed & delivered (120 sloped seating for training): here
Pergola Plan designed & delivered (Student meal & rest area): here
Steel for mezzanine, designed built & delivered to Hope College 7th December 2009.
Builder will now prepare teaching auditorium foundation and footing for installation.
Image of teaching auditorium where mezzanine will be constructed.
Carpet to be removed 14th December 2009 where Mezzanine is to be built.
Eight pads to be cut into the foundation hold mezzanine steel 15th December 2009
Outdoor location of where pergola will be built for students to have morning & afternoon teas and lunch time meals.
Mezzanine foundation being prepared for slab reinforcing 17th December 2009
Lecture room slab foundation reinforcement for 10 tonnes of seating structure Dec 09
Lecture room first steel strust December 2009
January 20th 2010 Lecture Room being built
Lecture room structure being built 20.01.10
February 4th 2010
Under Lecture room and entrance to lecture room gyprocked 4.2.10
Lecture Room with gyprock & electrical wiring almost complete 4.02.10
Lecture Room with gyprock nearing completion 4.02.10
Lecture Room seating structure with carpet and seat 4.02.10
Commencement of Outdoor pergola for student lunches 4.02.10
Outdoor lunch area with first concrete slab and post struts 4.02.10
Outdoor lunch area & pergola land preparation 4.02.10
Indoor Tiling and Painting 17.02.10
Outdoor Morning Tea & Lunch Area Progress 17.02.10
|